The Pont Pierre-Laporte ( Quebec City’s suspension bridge, completed in 1970, carrying Autoroute 73 between Sainte-Foy and Saint-Nicolas on the south shore ) is undergoing two major simultaneous rehabilitation programs in 2025-2026 that are significantly affecting traffic in the bridge corridor. The suspension cable replacement program (managed by the Jacques Cartier and Champlain Bridges Incorporated, JCCBI, which acquired ownership of the bridge structure in November 2024) and the $477.4-million north interchange reconstruction (managed by the Quebec Ministry of Transport) are the most significant infrastructure works in the Quebec City area since the Autoroute 440’s construction in the 1970s-1980s.
The Bridge: Basic Facts
The Pierre-Laporte Bridge spans 668 metres across the St. Lawrence Canada’s longest suspension bridge open to vehicular traffic when completed in 1970. Named after Quebec Labour Minister Pierre Laporte, murdered by the FLQ during the October Crisis of 1970 (the year the bridge was completed), it carries approximately 100,000 vehicles daily in both directions on Autoroute 73, making it the busiest bridge crossing in the Quebec City region. Its two main cables, each over 60 centimetres in diameter, support the deck carrying the highway. The bridge was designed and built by the engineering firm COWI (then Foundation Company of Canada) over four years of construction beginning in 1966.
JCCBI Acquisition & Cable Replacement
In November 2024, the federal government ( through JCCBI (the Jacques Cartier and Champlain Bridges Incorporated, the Crown corporation that manages the Jacques Cartier and Champlain Bridges in Montreal) ) acquired the Pierre-Laporte Bridge structure. This federal acquisition was motivated by the bridge’s strategic national significance and the need for sustained capital investment that the provincial government had committed to under the infrastructure cost-sharing arrangement. The cable replacement program ( a multi-year project to replace the bridge’s aging suspension cables ) began under this new ownership framework. The work requires scaffolding installations and periodic lane reductions on the bridge deck.
North Interchange Reconstruction: $477.4M
The reconstruction of the north interchange serving both the Pierre-Laporte and Quebec Bridges ( the complex highway junction on the Sainte-Foy shore where Route 175 and the bridge access ramps meet ) has a total project cost of $477.4 million, including a $6.3-million contribution from the Ville de Québec. Major disruptions include: the closure of the Avenue des Hôtels between Chemin Saint-Louis and the Aquarium parking area until autumn 2026; the closure of the Avenue des Hôtels access ramp to Route 175 southbound from April through July 2026; one lane in each direction on Route 175 between Exit 22 and Chemin Saint-Louis until December 2026; and lane reductions on multiple Autoroute Henri-IV (73) and Duplessis (540) ramps. A free shuttle service is provided during complete Quebec Bridge closures that periodically occur during the concurrent Quebec Bridge rehabilitation works.